Lake
County Judicial Center

Owner/Client:
Lake County Board
of County Commissioners
Location:
Tavares, FL
Completion Date:
2010
Project
Size:
446,646
gross square feet
Project
Cost:
$150,000,000 est.
Current
Phase:
Preconstruction
This multi-phased project in
downtown Tavares will expand and renovate the county
Judicial Center. The first phase of the project
includes a new 30,000 sf building for the offices of
the County Tax Collector and Property Appraiser.
Included with the office building is a new 1800
vehicle parking garage. A new central energy plant
facility will be completed at the same time as the
office building to service that facility.
The next phase will be
construction of a new 288,361 sf addition to the
Judicial Center. Once that is complete, another
120,620 sf of existing space will be completely
renovated. The facility will be LEED Certified.
Construction is projected to begin in June 2008.
Back
|
|
|